Title: BOM Availability Post by nigels on 04/22/03 at 06:36:23 Hi, We control the assembly of Printed Circuit Boards with a whole host of components. I create the BOM component by component so I can use the Reference field to identify the coimponent (eg R1 R2 etc) This means that I can have the same component on the BOM a number of times. When I run the BOM Availability, just as a quick check to see if I have ordered enough components (before I lock in the BOM by creating a WO) The program has no sense of what it is doing with these 'same' components, ie if we have a stock of 1, then even if it is used a 100 times on the BOM, because it is only used in 1's (one per line) it thinks we have suficient to perform a build ! It should perform a consolidation of the BOM before it tests the quantities. |
Title: Re: BOM Availability Post by Mike_Habich on 04/22/03 at 08:09:29 Other deficiencies: --Phantom assys always show shortages, even if components of phantom are in stock. --If you view multi-level, each subassy and component is listed and treated separately, with no logic connecting them. We had a custom written that corrects none of the above problems, but displays PO number, blanket release quantities, and dates expected . Very useful. |
Title: Re: BOM Availability Post by Lynn_Pantic on 04/23/03 at 12:03:47 Yes, I have an open programming request in - "BM-D Needs Major Overhaul" Will see what I can do about prioritizing it. |
ISTech Support Forum » Powered by YaBB 2.1! YaBB © 2000-2005. All Rights Reserved. |