http://www.istechforum.com/YaBB.pl Evo-ERP and DBA Classic >> Manufacturing >> PO item costs?? http://www.istechforum.com/YaBB.pl?num=1052828956 Message started by penz on 05/13/03 at 06:29:16 |
Title: PO item costs?? Post by penz on 05/13/03 at 06:29:16 Hi, I have a Make From item that is to be recieved via PO however it was just brought to my attention that the cost of the items need to go to a specific WO. If I known in advance I could've assigned a WO on the PO but now its to late, or is it? Can I modify the PO to assign the WO number or is there another method I should assign the item costs? Thanks Jim P. |
Title: Re: PO item costs?? Post by David Waldmann on 05/13/03 at 08:23:31 As long as you haven't applied the PO to an Invoice you can fix it. You will have to issue a negative receipt if it's already been received. Then you can just edit the PO and include the WO #. When you receive it you will see the WO# it's being received to. |