Post by Laura on 05/29/03 at 16:40:15

I have ordered something for a job.
The material is on the PO.
But we have not received it in yet
The part# from the unrecieved PO is shown on JC-B.
But the $ amt is not printing out on JC-B

What am I doing wrong?

Shouldn;t a projected report show unreceived costs?
Thanks,
Laura

Title: Re: JC-B projected-shows PO item# but not $ amt
Post by Lynn_Pantic on 05/29/03 at 16:47:09

The JC-B uses standard costs for the projected costs that have not yet been incurred.  I can certainly see the merit in using a PO price for items that have been ordered but not yet received.  Another one for the list.

Title: Re: JC-B projected-shows PO item# but not $ amt
Post by Laura on 05/29/03 at 17:04:37

Thanks.

Am I overlooking a report  (either in PO or JC) that would show  both received and unrecieved items that I could run by WO#  or SO#?

Thanks again.

Laura

Title: Re: JC-B projected-shows PO item# but not $ amt
Post by aricon on 05/29/03 at 18:55:22

Nope.  Although I had a client request EXACTLY that quite a while back.  We are probably going to end up doing it in MS Access.

Title: Re: JC-B projected-shows PO item# but not $ amt
Post by Laura Oliver on 11/17/10 at 16:16:50

went back thru the archives,   there are 3 other threads..... and one is mine
it looks like there may not be much interest in this.   But it would be nice to have this one day, if it is not too much trouble .

THANKS