http://www.istechforum.com/YaBB.pl Evo-ERP and DBA Classic >> Manufacturing >> MRP Order Action Aggregates http://www.istechforum.com/YaBB.pl?num=1081439829 Message started by matth on 04/08/04 at 07:57:09 |
Title: MRP Order Action Aggregates Post by matth on 04/08/04 at 07:57:09 When looking at the Order Action Report (MR-H), the MRP system appropriately splits up required Make and Buy actions based on required due dates. Is there a report or other way to look at aggregate totals required without adding them up myself? In other words, if I have 5 planned purchase or work orders for a particular part number, can MRP tell me the total quantity needed regardless of required production dates? Any assistance is much appreciated. Thanks. |
Title: Re: MRP Order Action Aggregates Post by Lynn Pantic on 04/08/04 at 08:28:28 The IS Tech Version of MR-J can be run in report only mode so if you leave all the dates blank, it will give you subtotals by item grouped by vendor as if it were going to generate POs but not actually generate them. Plan to do the same for WO, not done yet. |
Title: Re: MRP Order Action Aggregates Post by matth on 04/13/04 at 07:15:57 Thanks for your help. |
ISTech Support Forum » Powered by YaBB 2.1! YaBB © 2000-2005. All Rights Reserved. |