Title: MATERIAL ISSUES- BACKOUT
Post by normsnc on 04/19/04 at 12:37:44

I used the Dsp Material Trans button in WO-G to unissue material to a work order.  I highlighted the issue I wanted to unissue and hit the "enter" key, then hit the "F4" key to delete the issue, DBA prompted "Do you want to delete this record?", "Yes" The transaction is deleted but the material shows being issued when the work order is viewed in WO-A,  when JC-A is ran, and when viewing the part issued to the work order IN-A the material on-hand has the incorrect quantity.  Can someone please explain, or can it be fixed?

Thanks

Title: Re: MATERIAL ISSUES- BACKOUT
Post by Lynn Pantic on 04/19/04 at 12:50:18

You shouldn't have used the Delete button (in fact, the button shouldn't even be available at that point, let me have the programmer remove it!).  Once you have the record on the issue screen, hit Enter again and you will be prompted to back it out.  Say Y and all the related tables will also be updated.  

To fix what you have done, go to WO-I, bring up the WO, answer Y to the question about rebuilding the WO totals, and then Escape out without actually doing any Finished Production.

Title: Re: MATERIAL ISSUES- BACKOUT
Post by normsnc on 04/19/04 at 12:59:53

Thanks for the quick response Lynn

Lance