http://www.istechforum.com/YaBB.pl Evo-ERP and DBA Classic >> Manufacturing >> Sometimes an outside process http://www.istechforum.com/YaBB.pl?num=1107554799 Message started by timgolds on 02/04/05 at 14:06:39 |
Title: Sometimes an outside process Post by timgolds on 02/04/05 at 14:06:39 HELP!!! I can't figure out how to do this. Here's the senario. We have part that has four processes to it. One of the proccesses takes a while so we would like to farm it out when we are busy but not all the time. I have the raw material, of type R with a route built as follows to a type A part: 10 - saw to length 20 - lathe to spec 25 - outside process lathe - type A 30 - mill 40 - heat treat step 25 is an alternate step to replace step 20 when we don't have the bandwidth to do this step. How do I do a PO for this alternate step? I have tried a service PO but that wants a seq with type P. If it's a type P, it's assumed the outside process happens every time, which is not the case. If I do a purchase PO, it receives the unfinished part before the other steps are complete causing an even greater problem. Any suggestions or ideas would be a great help, Tim |
Title: Re: Sometimes an outside process Post by Lynn Pantic on 02/04/05 at 17:16:36 Use WO-K-A to change the type of the sequence for the WO to P when you need it, then you can do the Service PO. |
ISTech Support Forum » Powered by YaBB 2.1! YaBB © 2000-2005. All Rights Reserved. |