Message started by mwee on 05/26/05 at 06:57:04

Title: PL IN MRP ACTION REPORT
Post by mwee on 05/26/05 at 06:57:04

I WAS RUNNING MR-H. I GET PL 23, PL 60 INSTEAD OF WORKORDER NUMBER IN PEGGED TO COLUMN. SOME ONE WHO KNOW WHY AND HOW. WHAT IS THE ABBREVIATION OF PL  STAND FOR.
THANKS
MICHAEL ::) ::) ::)

Title: Re: PL IN MRP ACTION REPORT
Post by Lynn Pantic on 05/26/05 at 07:22:38

PL is for Planned Order - they are Work Orders MRP says you should create and, once you do create them, these are the components they will need.

Title: Re: PL IN MRP ACTION REPORT
Post by mwee on 05/26/05 at 08:52:45

Thanks Lynn
I found some explanation in Help section too.