Message started by kemkraft.com on 08/10/05 at 11:36:24

Title: IN-A Cost Question
Post by kemkraft.com on 08/10/05 at 11:36:24

When I look in IN-A at a parent part number, the last cost does not include the cost of the child parts required to make it, even though all the child parts have a last cost.
Q: Is there something I can do to so that parent parts include the costs of all the child parts?

Title: Re: IN-A Cost Question
Post by Lynn Pantic on 08/10/05 at 14:18:29

The Last Cost of an assembly is whatever the Last WO-I posting used as a cost, has nothing to do with the Last Cost of the components.  If the work order costing was incorrect, the Last Cost will also be incorrect.  See http://www.istechsupport.com/ts_mq3.asp