Message started by JNAPIER on 10/07/05 at 07:44:54

Title: Shotage Report On "Crack"
Post by JNAPIER on 10/07/05 at 07:44:54

I just looked at a shortage report after entering fin. prod. It shows it issued 8X the actual units issued on all 6 line items. The UOH number is correct and it did issue the correct amounts from Inv.

John

Title: Re: Shotage Report On "Crack"
Post by JNAPIER on 10/07/05 at 11:38:29

I just ran another batch. It is all random. some reports are correct and some 80% wrong with some lines correct. Same unit being backflushed on a separate WO different lines wrong, no pattern. Factor of difference are 2,3,4,5 and 9 times too many issues reported.

John

Title: Re: Shotage Report On "Crack"
Post by Lynn Pantic on 10/07/05 at 16:31:26

Is it only the shortage report that is wrong?  What about JC-E and the Materials button in WO-A?  Were these WO processed and backflushed using WO-I or WO-P?  Before or after the 9/25 update was installed?  Is this enough questions?  Will the Angels win the World Series?

Title: Re: Shotage Report On "Crack"
Post by JNAPIER on 10/10/05 at 05:08:22

The Padres will win it!!!

WO-A, JC-E, IN-A Transactions and Usage all correct Quan. Issued. The correct Quan. were reduced in UOH. This is after 9-25 UD. Very random and some WO with only one or two units short are listed correctly!

John

Title: Re: Shotage Report On "Crack"
Post by Lynn Pantic on 10/10/05 at 08:02:18

If you re-run a Shortage Report for a "bad" WO, does it show the same "bad" results?  

Title: Re: Shotage Report On "Crack"
Post by JNAPIER on 10/10/05 at 09:58:33


Lynn Pantic wrote:
If you re-run a Shortage Report for a "bad" WO, does it show the same "bad" results?  


WO-L-F? if so it shows the correct Quan. needed that WO.

John

Title: Re: Shotage Report On "Crack"
Post by Lynn Pantic on 10/10/05 at 10:55:38

So it is just the shortage report that runs immediately after processing the Enter Finished Production that is wrong?  WO-I or WO-P?  You never answered that part of the question.

Title: Re: Shotage Report On "Crack"
Post by JNAPIER on 10/10/05 at 11:27:23


Lynn Pantic wrote:
So it is just the shortage report that runs immediately after processing the Enter Finished Production that is wrong?  WO-I or WO-P?  You never answered that part of the question.


Wo-I, Does WO-P now print the shortage report? I like WO-P, Is their any known issues in it?  To recap, Yes it is only the report after WO-I.

John

Title: Re: Shotage Report On "Crack"
Post by JNAPIER on 10/10/05 at 11:48:43

Just Ran more. It appears that the same part # in the issue happens on other products the same. The factor in which it is off 2x 3x 5x whatever is the same on issues of different products using the same item #. That's clear as MUD. Rambling over!

John

Title: Re: Shotage Report On "Crack"
Post by JNAPIER on 10/14/05 at 11:21:10

One More pattern I notice. If I have a Quan. of 1 on the WO it reports correctly. 2 or more and many line items FREAK.