Message started by Dave Miller on 10/17/05 at 10:53:18

Title: PO-E ENTER RFQ
Post by Dave Miller on 10/17/05 at 10:53:18

I cannot get the program to routinely include the specifications. Sometimes it asks if they should be included - saying yes does not insure they are included,  sometimes it doesn't ask. I do not have the same problem in PO-A Enter POs. Any thoughts?

Title: Re: PO-E ENTER RFQ
Post by NovaZyg on 10/17/05 at 10:59:23

What version are you running? PO-A and PO-E are the same program. The PO-E menu just calles PO-A and tells it to open the rfq files not the standard PO files.


Title: Re: PO-E ENTER RFQ
Post by Dave Miller on 10/17/05 at 12:14:56

2005.1 with 9/25 update

Title: Re: PO-E ENTER RFQ
Post by Dave Miller on 10/17/05 at 12:16:40

It never fails in the PO-A process
It seems to alays include specifications after about the fourth item on a given RFQ - could it be in the RFQ form?