http://www.istechforum.com/YaBB.pl Evo-ERP and DBA Classic >> Manufacturing >> MRP is Hanging up http://www.istechforum.com/YaBB.pl?num=1136588625 Message started by shadowcaster on 01/06/06 at 15:03:45 |
Title: MRP is Hanging up Post by shadowcaster on 01/06/06 at 15:03:45 When generating requirments my MRP is stoping on the same Bom number when doing the Analysis. anyone got a sugestion on where to start ? opened the bom all looks well JW |
Title: Re: MRP is Hanging up Post by Lynn Pantic on 01/06/06 at 17:10:18 You have a loop in the BOM at a lower level - something is a component of itself a couple of levels apart. Use SM-J-Q. |
Title: Re: MRP is Hanging up Post by shadowcaster on 01/07/06 at 08:32:40 about how long will this take its been running a few hours jw Update: I after got back from the Pats game it was done !! Go PATS !!! Lynn was correct I had nested a bom with my cut and paste quick quick bom editing. Thanks again Lynn you saved the day again !! J dub |
ISTech Support Forum » Powered by YaBB 2.1! YaBB © 2000-2005. All Rights Reserved. |