Title: SA-B proft by invoice - average cost Post by Laura Oliver on 02/21/07 at 13:51:37 Can I make SA-B use actual costs? If we take way too long or kill a piece of material, then this in no where near accurate. I like the speed and simplicity of SA-B (not found in JC, which uses actual costs) Thanks, Laura |
Title: Re: SA-B proft by invoice - average cost Post by David Waldmann on 02/22/07 at 05:25:27 Unless you have the add-on program that processes WO at Invoice Posting, Average is the cost that DBA uses on the Invoice. Therefore SA-B is correctly reporting what DBA actually did. |
Title: Re: SA-B proft by invoice - average cost Post by Laura Oliver on 02/22/07 at 06:47:25 Does this ADD-ON program reflect both received and unrecieved PO's? JC-A shows PO-I-E, but not PO-I-A. Often we invoice our customer before our vendor has invoiced us. We dont receive POs in until we have comfirmed PO matches actual paper invoice. |
Title: Re: SA-B proft by invoice - average cost Post by David Waldmann on 02/22/07 at 06:57:03 Automatic Work Order Processing at Invoice Posting - This program enters finished production, backflushes components and closes the work order automatically based on work order default settings when invoices are posted. Applicable for single level of BOM only and only when work orders are created using SO-N, Convert Sales Orders to Work Orders. Guarantees that cost associated with the invoice line is from the correct work order and not skewed by average cost of other items in stock. Free 30 day trial available. Subscriber Price $249.95 Non-Subscriber Price $399.95 from http://www.istechsupport.com/addonsales.asp |
Title: Re: SA-B proft by invoice - average cost Post by Lynn_Pantic on 02/22/07 at 07:03:15 You will never have accurate costs at the time of invoicing if you don't receive the PO's. I suggest you receive the POs and Enter Finished Production prior to invoicing so the costs are accurate (to the degree your PO is accurate). Any subsequent change resulting from a difference between the PO and Invoice will be reflected as WIP Variance but will ultimately be shown in the JC reports. If Purchasing is doing their job, it should be the rare exception that the AP Invoice is significantly different from the PO. |