http://www.istechforum.com/YaBB.pl Evo-ERP and DBA Classic >> Manufacturing >> outside processes & cost roll-up http://www.istechforum.com/YaBB.pl?num=1173219527 Message started by heliosquare on 03/06/07 at 14:18:47 |
Title: outside processes & cost roll-up Post by heliosquare on 03/06/07 at 14:18:47 Is there a way to roll up costs using the last cost as opposed to the standard or average costs? The last cost field in IN-A is correct for parts with outside processes (via service PO's) but I don't see any way of accurately rolling up a parent part that contains lots of parts that contain outside processing charges. |
Title: Re: outside processes & cost roll-up Post by heliosquare on 03/06/07 at 15:29:31 sorry, stupid question...I see BM-H allows the choice b/w average and last cost... :-[ |