We have started to use MRP and have loaded in a forecast for the year, but I have a couple questions. We have product that we forecast and then product that we build to order from the sales orders that come in. My first question is after a month goes by should we delete the forecast? Also should we be consuming the forecast with S.O's or not beings we forecast some of our product and some we don't.