Title: WIP variance and the BS Post by cathyh on 08/23/07 at 10:33:24 Work order finished on 8/21 and closed on 8/22 with a WIP variance of -22.31. Business Status does not post this change to the WIP Balance. |
Title: Re: WIP variance and the BS Post by cathyh on 08/29/07 at 08:45:33 Has anyone looked at this? We routinely finish a Work order at actual cost and then add more costs before closing. The added costs go into WIP Variance. The field in the Business status for FP/VAR reflects the FP total but not the Var total, and the WIP balance is wrong. |