Message started by lynnkissinger on 05/16/08 at 15:46:46

Title: Make from parts
Post by lynnkissinger on 05/16/08 at 15:46:46

Should the last cost and/or average cost of a make from part represent only the cost to "make" the new part or should it include the cost of the part sent and the add't make cost.  Example:  we send a part to be painted, the cost of the part prior to painting is 1.00, we pay the vendor .50 to paint.  Should DBA show the last cost as .50 or 1.50?

Title: Re: Make from parts
Post by GasGiant on 05/16/08 at 20:38:35

The resulting part in stock should collect all costs that went into it.

Title: Re: Make from parts
Post by Lynn_Pantic on 05/18/08 at 13:53:02

The Average cost will reflect the rolled up cost of the components but the Last Cost is just the processing cost.