Title: Closed PO's showing on RNI report Post by MBG on 05/07/09 at 14:57:34 There are three items on the RNI report PO-I-F that are from purchase orders that are closed. I ran POKFIX and RNIFIX, but there was no change in the report. |
Title: Re: Closed PO's showing on RNI report Post by hattox on 05/27/09 at 12:49:38 Once a PO is closed, and is subsequently re-opened, the received items are put back in RNI to be paid. (I know, it doesn't make sense to me, either.) However, you can get rid of these items by invoicing them through AP-C, then enter a "fake" credit memo for the total dollar amount, then write a "fake" check for zero dollars. Darlene Hattox Admyr Wireline, Inc. |
Title: Re: Closed PO's showing on RNI report Post by Lynn_Pantic on 05/29/09 at 18:50:46 The bug with items going back on the RNI report after reopening a closed PO was fixed a while back. |
Title: Re: Closed PO's showing on RNI report Post by Juan on 09/21/09 at 10:55:46 How you guys solve this problem? How you clean the RNI report? we still have order that had been close, but they still show on the report Thx Juan |
Title: Re: Closed PO's showing on RNI report Post by Lynn_Pantic on 09/21/09 at 13:09:01 If the order is currently closed, then it should not be on the report. UT-A, POKFIX and UT-A, RNIFIX may help. Also, if you are running RNI report as of a prior date, the closed POs don't come off until the effective clsoe date. |
Title: Re: Closed PO's showing on RNI report Post by Juan on 09/21/09 at 13:50:10 Thx, I'll try that |
ISTech Support Forum » Powered by YaBB 2.1! YaBB © 2000-2005. All Rights Reserved. |