http://www.istechforum.com/YaBB.pl Evo-ERP and DBA Classic >> Manufacturing >> WO-K-B recalcuate modified BOM http://www.istechforum.com/YaBB.pl?num=1255622424 Message started by dbernhard on 10/15/09 at 09:00:23 |
Title: WO-K-B recalcuate modified BOM Post by dbernhard on 10/15/09 at 09:00:23 Hi When you have to modify a WO BOM and you go into WO-K-B to delete or add components the system does not recalculate the estimated cost - it recalculates the actual cost - yet what I need to have the new estimated cost recalculated. It requires an additional step of going back into the original work order - WO-A - and re-estimating Do you think that the EVO experts could program this to recalculate the estimated cost? Is there a better way? Thanks Debra |