On the DC-B window you can enter production only.  (Nice!!)
But how do you tell the system that the sequence is close (Done!)

You have to go into the DC-G to edit that labor transaction there you can tell the system that the sequence is  done.
This does not make sense, it is impractical. That question should be ask on the DC-B window.

Are we following the proper steps?

We want Evo Schedule to know that the sequence is done therefor that machine center is "free" for the next Work Order.

Please advice

:-[

Kelloggs

Title: Re: Scheduling Work Orders - DC-B
Post by Kelloggs on 08/21/12 at 06:42:43

Anyone using Evo's Schedule?
How are you guys handling it?

:'(

Kelloggs

Title: Re: Scheduling Work Orders - DC-B
Post by Lynn_Pantic on 08/23/12 at 14:03:52

Scheduling has a default for "PO & DC to update Start and Finish Dates of sequences." that will mark the sequence as complete based on the quantity completed.