Is it possible to update the Last Cost of an item after a PO has been received and closed?

Title: Re: Update Last Cost after PO has been received
Post by Lynn_Pantic on 09/03/14 at 07:58:58

IN-K can be used to edit Last Cost.

Title: Re: Update Last Cost after PO has been received
Post by Ashley on 09/03/14 at 09:14:47

Thank you for the quick reply!