http://www.istechforum.com/YaBB.pl Evo-ERP and DBA Classic >> Items >> Change Cost http://www.istechforum.com/YaBB.pl?num=1431366679 Message started by GoodNatureProducts on 05/11/15 at 10:51:19 |
Title: Change Cost Post by GoodNatureProducts on 05/11/15 at 10:51:19 I have a part that was bought from the outside and we have a $$ amount in the outside proc field, we now just buy the material and assemble the part. My Material cost field is correct but I cant make the outside proc = 0. It will not let me change it in IN-B or IN-L-A thanks |
Title: Re: Change Cost Post by Vman on 05/12/15 at 09:43:11 Try UT-A FIXSTD.RUN. |