Title: Forecast missing in MRP Post by gtladmin on 07/30/15 at 09:01:12 When purchasing prints MRP in one company, forecasts aren't showing up but total forecasted number shows up on the inventory screen. They made sure the option was Y to include forecasts but it won't show them. Purchasing says there is only one forecast and none of the BOM items for it are showing a forecast. Not sure if another forecast was entered if that would work or not. So it's no specific part but only the BOM items for that forecast. Example: when you enter a forecast, like "50 of ILT5000/U for 8/5 and 50 for 10/5" it then makes the report show a requirement for those dates for every item on that upper level item's BOM. And NONE of those BOM items are showing a forecast. They are pretty sure this did work at some point, and of course no one changed anything, so I am tasked with trying to figure out WHAT CHANGED??? I have no idea where to start looking.. HELP! Thanks in advance, Val |
Title: Re: Forecast missing in MRP Post by gtladmin on 08/04/15 at 14:39:35 Ummmm....anyone have any ideas hear? We will try deleting and re-entering the forecast on the part, but just wondering what may be the real issue, if anything. Kind regards, Val |
Title: Re: Forecast missing in MRP Post by gtladmin on 08/05/15 at 07:41:08 Ok, so the production manager re-created the forecast and lo! He noticed that the setting for the item was "R" and not "F:. Explains everything....it's working now. "But nothing got changed, it was Evo!" Uh huh..... ::) |
ISTech Support Forum » Powered by YaBB 2.1! YaBB © 2000-2005. All Rights Reserved. |