Title: Capacity Planning for Incoming Inspection Post by RickS on 09/02/08 at 08:07:00 Looking for a means of totaling labor hours to inspect parts (adding Incoming Inspection with Inprocess Inspection) for each week for 1 – 12 weeks out for capacity planning Currently we compare our Open PO Report with time required to inspect the parts at Incoming Inspection. We create a matrix based on open PO and estimated hours to inspect the part (based on history). We compare the Open PO Inspection Labor Report against the Inprocess-Inspection Labor Report to look at capacity requirements. |