I was more than willing to "pony up", how b'out U?
Posts: 634
Gender:
|
I'm having some problems with BOM's that have a given Item # on two different lines. This is necessary because, in some cases, we use an item in sequence 10, and then another one of those same items in sequence 30 of the routing. We kit issue items for WO's when we release them. We un-issue items that are out of stock so that the shortage report for a WO is accurate. It seems that on WO BOMs for these items, sometimes, the first item shows 1 required, and 2 issued. The second identical item # shows 1 required, and 0 issued. I would think that these would net out ok. However, when I try and close these types of work orders, it indicates that not all items have been issued. Is this situation just not handled correctly, or do we need to do something different?
|