Some of our routers specify "Outside Services".  A PO for the outside service is written and referenced to the Work Order number.  When the items are received from the vendor, the quantity doubles.  This requires going to DC "Enter Production Only" and backing out the incorrect quantity.  This is not an occasional problem.  It happens on every outside operation.
 
What are we doing wrong?
 
Back to top
 
 
  IP Logged
normsnc
Member
**


I love YaBB 1G -
SP1!

Posts: 53
Re: Outside Vendors
Reply #1 - 02/13/04 at 14:02:58
 
When you go to PO-A Enter Purchase Order and after selecting your vendor, does a window pop up to choose whether this is a P-Purchase type PO or a S-Service type PO?  Choosing a P instead of an S might be your only problem here.
Back to top
 
 
  IP Logged
dwight
Browser
*




Posts: 4
Re: Outside Vendors
Reply #2 - 02/13/04 at 14:34:51
 
Thanks for your reply.  We do use as "S" type order for outside service.  Apparently this is not the problem.
Back to top
 
 
  IP Logged
Karen Mason
Active Member
*****


Ain't life grand!?!

Posts: 728
Gender: female
Re: Outside Vendors
Reply #3 - 02/13/04 at 15:02:02
 
Do you use the conversion factor?  If so, is it being figured properly?  For instance heat treat is by the pound, so if we have 500 pieces at 1000#, the conversion factor = .50    (pcs/wt).  On the receiving end, make sure the weight is being received.
 
Other than that, ours seems to work okay
Back to top
 
 

Karen Mason, Vice President
Bula Forge & Machine, Inc.
1-60# forgings, machining, & assembly
Cleveland, OH
Tel:216-252-7600 Fax:216-252-7601 www.bulaforge.com
EVO-ERP 09/16/09 SP2
Email WWW   IP Logged
dwight
Browser
*




Posts: 4
Re: Outside Vendors
Reply #4 - 02/13/04 at 15:13:35
 
All our Outside Service PO's are entered as dollars per piece.  Maybe our problem has to do with the way the router is set up.  Eg.
 
   Operation 30 - Mill
   Operation 50 - Outside Service
   Operation 60 - Receive from Vendor
   Operation 90 - Receive from Work Order
Back to top
 
 
  IP Logged
Lynn_Pantic
Administrator
*****


evolution (n) -
gradual change to a
different form

Posts: 5663
Re: Outside Vendors
Reply #5 - 02/16/04 at 10:43:44
 
If you have 2 operations set up, one to send the parts out and one to receive them back in, then that could be a problem.  There should be one operation for the plating or painting or whatever the vendor is doing, devined on the Routing as a type P meaning Outside processing.  Cutting the PO sends them out and receiving the PO brings them back.
Back to top
 
 

Lynn Pantic
IS Tech Support
lynn@istechsupport.com
Email   IP Logged
dwight
Browser
*




Posts: 4
Re: Outside Vendors
Reply #6 - 02/19/04 at 12:55:08
 
Lynn,
 
Thanks.  Our problem was that the outside order was issued once, when the PO was cut.  (We didn't know that actually Issued the material.)  The items were Issued again when the warehouseman "clocked in" the pieces on the operation number on the router.