matth
Browser

I love YaBB 1G - SP1!
Posts: 3
|
When looking at the Order Action Report (MR-H), the MRP system appropriately splits up required Make and Buy actions based on required due dates. Is there a report or other way to look at aggregate totals required without adding them up myself? In other words, if I have 5 planned purchase or work orders for a particular part number, can MRP tell me the total quantity needed regardless of required production dates? Any assistance is much appreciated. Thanks.
|