sharon krewson
Ex Member



MRP Regeneration
10/15/04 at 10:53:01
 
Hi. Sometimes when we do our MRP regeneration, it doubles all the demand & supply on the reports. Has this happened to anyone? Does anyone know why it happens?
Back to top
 
 
  IP Logged
Cyndee Pappas
Senior Member
****


EVO~ERP 2006.1
02/28/06 update

Posts: 258
Gender: female
Re: MRP Regeneration
Reply #1 - 10/15/04 at 11:01:19
 
I've seen this happen when multiple folks are working with MRP. I'm not sure if they were both Generating MRP or if one was just looking at reports. If we Generate again, it goes back to normal.
Back to top
 
 

Cyndee Pappas
Industrial Data Systems
EVO~ERP 2006.1 with 02/28/06 update
Client/Server Win2000 Server
Pervasive SQL 2000i

WWW   IP Logged
sharon krewson
Ex Member



Re: MRP Regeneration
Reply #2 - 10/15/04 at 11:10:13
 
Thanks.  That scenario is very likely here and makes sense.
Back to top
 
 
  IP Logged
shadowcaster
Active Member
*****


I'm not here because
I know what to do.

Posts: 678
Gender: male
Re: MRP Regeneration
Reply #3 - 10/21/04 at 14:47:07
 
same thing happens here when 2 people do it at the same time
 
JW
Back to top
 
 
WWW   IP Logged
Lynn_Pantic
Administrator
*****


evolution (n) -
gradual change to a
different form

Posts: 5681
Re: MRP Regeneration
Reply #4 - 10/21/04 at 15:18:14
 
Yes, that would do it.  The first thing MR-F does is clear the file so it starts with an empty file.  If it can't clear it (because another user has it open) then it ends up appending to the existing records.  I can look into ways to prevent that from happening.