You can either enter a from/through range or a list of work orders and quantities. If you select the range then the program assumes all work orders have been completed for the original WO quantity and they are processed in reverse so if for example you specify a range of 6013-1 through 6013-27 it will start with the -27 and work backwards. This way, if multi-level assembly work orders had been created using WO-K-D or SO-N, the lower level assemblies get processed first.
|