klconard
Browser
Posts: 6
|
We buy the completed assembly from our vendor as a "Purchased Part", we don't build it in-house. I know I can do a negative purchase order, then change the part from purchased to make from, make a bill of materials, then a positive purchase order, etc. What we really want to be able to do is make a work order for the purchased part number, then the bill of materials would include that purchased part number plus whatever parts it took to change the wrong internal component(s). That way it pulls the purchased part from our inventory, pulls the part(s) necessary to fix it, and adds the costs together and then puts it back into inventory as the original part number, at the higher price, when we close the work order at "Enter Finished Production".
|