Hi, I'm running the Std. Labor Hrs. report and the Std. hours are funny. I have a sequence thats the standard calls for 1 hour to complete by one person, however two people actually worked on it for an hour each. They both put qty. 1 complete when they logout. The standard report will show a standard of an hour each which gives the total std. time 2 hours, however the std. should stay at 1 hour in theory. is there anything I can do to get the report to show the set std. hours? Thanks Jim P.
|