Make From cost in WO (Read 215 times)
cathyh
Active Member
*****


I used to be
indecisive; now I'm
not so sure......

Posts: 1210
Gender: female
Make From cost in WO
06/14/06 at 07:35:07
 
We have a part that is a "make from" which has costs for outside labor and a part we stock.  When I print the costed BOM for the part we use the M type part in, the outside processing shows in the line for the make from and the 2nd level part cost shows under that.  
In the work order, the cost for the make from only includes the cost of the item, and not the outside processing cost. WE have never had a problem with make froms in the ordering stage, however there seems to be a problem in the estimated costs of a work order using this part.  This is a problem because the variance from standard is not correct for a work order without the considerable cost for outside processing showing up in the cost of the M type part.
Have we set up this part number incorrectly?
Back to top
 
 

Cathy Hamilton
Wing Inflatables, Inc.
EVO-ERP2008.1(20 users) w/IS Tech update 5/25/09 (as of 08/21/09)
Windows 2008 Server/client
Pervasive V10.1
Email WWW   IP Logged
cathyh
Active Member
*****


I used to be
indecisive; now I'm
not so sure......

Posts: 1210
Gender: female
Re: Make From cost in WO
Reply #1 - 06/14/06 at 09:38:24
 
Well I figured out which report I was misreading so ignore the whole topic! embarrassed
Back to top
 
 

Cathy Hamilton
Wing Inflatables, Inc.
EVO-ERP2008.1(20 users) w/IS Tech update 5/25/09 (as of 08/21/09)
Windows 2008 Server/client
Pervasive V10.1
Email WWW   IP Logged
Pages: 1
Send Topic Print