I am having some mysterious changes being made to our standard costs on several component items. Since (as far as I know) only the owner and I know how to use the 'Run Program' feature to access the Standard Costs update program, I do not believe that anyone is deliberately changing our standard costs. Several of the changes were made when we were solely using Classic, and one has been since installing Evo. However, I am the only user currently using Evo. As such, I cannot pinpoint it as being either a Classic-only or Evo-only problem. Worse, 2 happened when receiving a PO and 1 when making an adjustment so I don't know which program cause it or if there is a common subroutine between PO Receipts and Invty Adjustments that could be the culprit.
Look below at what I am seeing and see if anyone else is having these problems. I would appreciate any advice anyone has to offer on what could possibly be causing these changes to our Standard Costs.
This first image is from March when we were only using Classic. The Std Cost is mysteriously rounded to 2 decimal places on this Purchase Receipt and for all transactions going forward. Don't know why--we generally only reset our Std Costs after year-end. The BOM was not updated/re-rolled with this change which we normally do whenever a change to Std Cost occurs.
Below is an adjustment from March where the Std Cost was once again rounded to 2 decimal places for all transactions going forward. Again, BOM was not updated so don't know how this could have happened. Using Classic at the time
Below is another Purchase Receipt. This time I was using Evo. The Std Cost mysteriously went to zero. By luck I found it, reversed the PO, fixed the Std Cost, and re-received the PO.
Like most companies, I have hundreds of items. While I used Inventory Listing to quickly scan thru and look for any more zero's (that's how I found the one above), I have no easy way of finding the rounding issues above. Too, with no warning of when this happens, my costs get screwed up and I don't find it until I begin looking for month-end discrepancies. Some of the discrepancies are just pennies or fractions of pennies per finished item so they're easily ignored. My bulk items may contain hundreds of components per finished item so the discrepancy ends up being several dollars per unit. Multiply that by hundreds of units per month and my discrepancy can easily end up being thousands of dollars. This makes me

!
Has anyone else out there experienced any mysterious changes to their standard costs like the one's I'm seeing above?
Chris