Scrapping Parts From Inspection
06/05/07 at 13:09:52
 
Does anyone know how to Scrap parts in Receiving Inspection.  Example: 100 parts received into "QC Receiving" and QC Receipt Traveler Printed.  95 parts are good and 5 no good.  However, instead of rejecting them (this reopens qty on purchase order by amount rejected), I want to show them as received and scrapped, but not go into inventory. If I use the qty "Us As Is", these parts go into inventory.  I know I can use various "scrap codes", but inventory is still updated.
 
Thanks Huh
Back to top
 
 

Dennis Wilkinson
IS Tech Support Contractor
dwilkinson@istechsupport.com

IS Tech Support Update 2022.1
PSQL Workgroup, Zen 14
Windows 11, Home Premium
  IP Logged
GasGiant
Administrator
*****


How can I help?

Posts: 1517
Gender: male
Re: Scrapping Parts From Inspection
Reply #1 - 06/05/07 at 13:26:09
 
Are you going to pay for them? If so, then you can receive them so that AP can pay for them, but make an adjustment to scrap them at the same cost as on the PO. If not, you can reject them and reduce the PO quantity by the number you scrap so that it will close.  
 
It's in or out. There is no Limbo  Wink
Back to top
 
 


Email WWW GasGiant GasGiant 31012781 swordworlder swordworlder   IP Logged
Dennis Wilkinson
Full Member
***


Life is Good :o)

Posts: 148
Gender: male
Re: Scrapping Parts From Inspection
Reply #2 - 06/06/07 at 06:23:25
 
Colin,
 
Yes, I plan on paying for the part so AP is all set.  I just wanted to know if I can scrap (reduce PO Qty & not increase inventory) during the receiving transaction processing or do I have to do an inventory adjustment after receiving.  From what I hear from you, I can receive complete and then scrap out of inventory via a second transaction.  Is that right?
 
Thanks,
 
Dennis
Back to top
 
 

Dennis Wilkinson
IS Tech Support Contractor
dwilkinson@istechsupport.com

IS Tech Support Update 2022.1
PSQL Workgroup, Zen 14
Windows 11, Home Premium
  IP Logged
Lynn_Pantic
Administrator
*****


evolution (n) -
gradual change to a
different form

Posts: 5663
Re: Scrapping Parts From Inspection
Reply #3 - 06/06/07 at 15:48:57
 
Yes, you have to do it as a 2 step process.
Back to top
 
 

Lynn Pantic
IS Tech Support
lynn@istechsupport.com
Email   IP Logged
Dennis Wilkinson
Full Member
***


Life is Good :o)

Posts: 148
Gender: male
Re: Scrapping Parts From Inspection
Reply #4 - 06/07/07 at 05:45:28
 
Lynn and all,
 
Thanks.
 
Dennis
Back to top
 
 

Dennis Wilkinson
IS Tech Support Contractor
dwilkinson@istechsupport.com

IS Tech Support Update 2022.1
PSQL Workgroup, Zen 14
Windows 11, Home Premium
  IP Logged
Pages: 1
Send Topic Print