Prepayment of unreceived PO (Read 622 times)
celesco corp
Browser
*




Posts: 7
Gender: male
Prepayment of unreceived PO
11/13/07 at 16:26:12
 
Sorry for being the newbee, but I  need to create a check to pay for tooling that is part of a PO.  I need to pay a 50% depositon the tooling only for them to start, so I cannot receive the line yet.  How do I issue the check while keeping the integrity of the PO/AP and the receipts associated with it.
 
TIA,
Rich
Back to top
 
 
  IP Logged
Cyndee Pappas
Senior Member
****


EVO~ERP 2006.1
02/28/06 update

Posts: 258
Gender: female
Re: Prepayment of unreceived PO
Reply #1 - 11/13/07 at 16:50:14
 
Back to top
 
 

Cyndee Pappas
Industrial Data Systems
EVO~ERP 2006.1 with 02/28/06 update
Client/Server Win2000 Server
Pervasive SQL 2000i

WWW   IP Logged
Dawn
Full Member
***


I love YaBB 1G -
SP1!

Posts: 156
Gender: female
Re: Prepayment of unreceived PO
Reply #2 - 11/26/07 at 14:06:28
 
When I purchase tooling with 50% down, I enter in the PO like normal and print 2 copies with the full amount - one that will go with the check to the vendor and one for my records.  I then receive in .5 and enter as normal.  I use the PREPAID as the Invoice number (what you would normally receive from the vendor) and cut check as normal.  Then when it comes time to make the final payment I just receive the remaining .5 and continue as normal  I try not to use the prepayment method as described above because it causes to much confusion and time.  The only exception I would make is if you are not going to recieve this tooling for a long time and it is a large dollar amount that could have big affect on your income statements.  Otherwise I don't worry about it.  Besides the more expenses you have the less you have to pay in taxes.  Unless your bosses are getting bonuses/raises based on profits then they might want to see it as a prepayment.  Smiley Smiley
Back to top
 
 

Dawn
Classic - 7/5/10 update
WWW   IP Logged
Theran
Member
**


I'm not a browser,
I'm a low end Bronze
member...

Posts: 70
Gender: female
Re: Prepayment of unreceived PO
Reply #3 - 11/26/07 at 17:38:15
 
I use the same method as Dawn.  Some items I purchase may have progress payments and just receive the PO for the percentage of the progress and process a payment against it.  It works well for us.
Back to top
 
 

Teres Heran
Armature Coil Equipment, Inc
DBA Classic, Ver 2004.1 with IS Tech 9/21/07
Email WWW   IP Logged
lmk223a
Senior Member
****


Accountant

Posts: 377
Re: Prepayment of unreceived PO
Reply #4 - 11/27/07 at 07:37:45
 
From Dawn - When I purchase tooling with 50% down, I enter in the PO like normal and print 2 copies with the full amount - one that will go with the check to the vendor and one for my records.  I then receive in .5 and enter as normal.  I use the PREPAID as the Invoice number (what you would normally receive from the vendor) and cut check as normal.  Then when it comes time to make the final payment I just receive the remaining .5 and continue as normal  
 
Another option: we make two lines on the purchase order - one line for the 50% down payment on tooling, and a second line for the remaining 50% due.  We use this for tooling, machinery or anything else with special payment terms. Then receiving processes the receipt of the line for the down payment so that the invoice can be processed through AP-C.  This eliminates the need for receiving .5 of a quantity of one.