From Dawn - When I purchase tooling with 50% down, I enter in the PO like normal and print 2 copies with the full amount - one that will go with the check to the vendor and one for my records. I then receive in .5 and enter as normal. I use the PREPAID as the Invoice number (what you would normally receive from the vendor) and cut check as normal. Then when it comes time to make the final payment I just receive the remaining .5 and continue as normal Another option: we make two lines on the purchase order - one line for the 50% down payment on tooling, and a second line for the remaining 50% due. We use this for tooling, machinery or anything else with special payment terms. Then receiving processes the receipt of the line for the down payment so that the invoice can be processed through AP-C. This eliminates the need for receiving .5 of a quantity of one.
|