cathyh
Active Member
   

I used to be indecisive; now I'm not so sure......
Posts: 1210
Gender:
|
We have a work order that has been delayed for 4 months. Parts and labor have been issued to it. Is there any way to change the date MRP uses to generate requirements for this work order? I assume this is the actual start date. I seem to remember a problem with changing the start date when parts and labor have been issued to it. How do others deal with this, other that just trying to ignore all the expedited buys listed in the order action report? It is too bad we can't tie the MRP generation to the start date of the sequence that this part is used in... I guess that is one for the update suggestions.
|