When you finish a partial work order, depending on what you use for the cost per item, (standard cost, DBA calculated approximate actual cost, or your own estimated cost), there may be a difference between the cost you use for the partial and the actual cost per item when the work order is completely finished. This difference posts as a variance, either positive or negative depending on whether the costs you used are understated or overstated.
|