MRP Generate Work Orders Start/Finish date (Read 551 times)
btaylor
Browser
*




Posts: 32
Gender: male
MRP Generate Work Orders Start/Finish date
02/25/14 at 11:13:22
 
I have just recently started using MRP to generate work orders for items we stock. I have min order quantities and reorder levels set for items we stock but I do not use lead times. When I generate work orders after running MRP it always wants to set the start and finish date based on the sales order date that triggered the need. I can manually edit finish date and set it to current date during review of the work orders but cannot edit start date (and even manually changing finish date is a pain). Is there a way to have it default to just using the current date for both start and finish dates for the work orders I want issued? Is there a default I am missing?
Back to top
 
 
Email   IP Logged
Lynn_Pantic
Administrator
*****


evolution (n) -
gradual change to a
different form

Posts: 5663
Re: MRP Generate Work Orders Start/Finish date
Reply #1 - 02/25/14 at 12:09:24
 
MRP is time based.  You need to define Lead Times.