I have a situation where I want to forward schedule and use finite scheduling too. I have 9 work orders set up, each with 1 operation, and all using the same work center. This one work center is set up to use finite scheduling and 8 hours capacity. I am running SH-E Finite Scheduling, hitting Re-Process and Go, and nothing happens. The Sched Start date does not change and all the Sched Finish dates show 00/00/00. Am I missing a step? Anyone have any ideas? Thanks.
|