Creating Staging Work Centers (Read 560 times)
bssSam
Browser
*




Posts: 3
Gender: male
Creating Staging Work Centers
08/13/08 at 07:56:55
 
Good Morning All,
 
     I am currently in the process of starting up a routing program for my company.  I have come a crossed something that I need some advice.  When creating work centers in the RO- module it seems to only allow me to set ops for 5 WC's at once per unit involved in the routing (op 10-50).  Is there any way to allow for more WC's to be set in the ops list because we want to have traceability while a unit is in the staging area of a department. For example, WC - Test Department (currently being tested) / WC - Test Department Staging Area (awaiting testing).
 
 
Thank you,
Brad Schoolcraft
 
Back to top
 
 

Brad Schoolcraft
Saminco Inc.
bschoolcraft@samincoinc.com
Email   IP Logged
Lynn_Pantic
Administrator
*****


evolution (n) -
gradual change to a
different form

Posts: 5663
Re: Creating Staging Work Centers
Reply #1 - 08/13/08 at 08:03:44
 
Not sure why you think you can only have 5.  The sequence number is a 3 digit number, so you can have up to 999 sequences per part.  You can set up as many different work centers as you need in RO-C.
Back to top
 
 

Lynn Pantic
IS Tech Support
lynn@istechsupport.com
Email   IP Logged
bssSam
Browser
*




Posts: 3
Gender: male
Re: Creating Staging Work Centers
Reply #2 - 08/13/08 at 08:35:51
 
I have created 10 WC's (set to Parent) and when I enter a routing for a part and go to specify the sequence it only pulls up 5 of the 10 in the OPs list.  Some option that I'm missing here?  I tried comparing the ones on my sequence list to the ones i have created and they are identical.
Back to top
 
 

Brad Schoolcraft
Saminco Inc.
bschoolcraft@samincoinc.com
Email   IP Logged
Lynn_Pantic
Administrator
*****


evolution (n) -
gradual change to a
different form

Posts: 5663
Re: Creating Staging Work Centers
Reply #3 - 08/13/08 at 09:01:09
 
You don't have to pull the sequences from the Operation Templates (which is what you are looking at in the list), you can manually enter whatever you want.  You can also create more templates in RO-I.
Back to top
 
 

Lynn Pantic
IS Tech Support
lynn@istechsupport.com
Email   IP Logged
bssSam
Browser
*




Posts: 3
Gender: male
Re: Creating Staging Work Centers
Reply #4 - 08/13/08 at 10:11:42
 
Thanks Lynn you resolved my problem.