GinaR
Browser

Anything Worth Doing is Worth Doing Right
Posts: 33
Gender:
|
I am needing to be able to quickly determine the actual cost of materials used, as a total, for all work orders closed during a specific time period. For example, I would like to know the ACTUAL cost of materials used in the manufacturing process during March 2018; however, I cannot seem to find a specific report or a quick way to drill down to those costs in any of the standard reports. Any report I have attempted to use, for example the Finished Work Order Report, is only a summary of those work orders closed. I do not really want to have to sort through 78 pages of job reports to determine which of those are actual closed work orders during the request time period and then have to manually calculate the cost of materials. Do any of our report Gurus have experience with this type of reporting? Thank you!
|